Supplier Cost Adjustment Budget Accounts
Summary: Budget Account is not derived correctly in case of Supplier Cost Adjustments
Content (please ensure you mask any confidential information):
We are facing an issue during Supplier Cost Adjustment. We transfer supplier cost from Project A to Project B through PPM. The system doesn't derive Budget Account for Adjustment Entry.
For example, Transfer $100 from Project A to Project B
Original Transaction of Project A: $100
Budget Account: Fund 101 Department 1100 Expense Account 50102
Reversal Transaction of Project A: - $100
Budget Account: Fund 101 Department 1100 Expense Account 50102
Adjustment Transaction of Project B: $100
Budget Account: System doesn't derive it from the original transaction unless you write a TAD rule. TAD has a limitation that it doesn't derive Budget Account from Imported Raw Cost. So, how do we derive budget account?