Supply Planning not suggesting plan order when project available balance is below safety stock
Summary:
Our client has several FG items that are MRP Planned and have safety stock quantity (user defined) loaded in MRP Plan. When the projected available balance is below safety stock, we're expecting a plan order to be suggested by planning. However, we're seeing this very inconsistently. Some items we get projected available balance when it's going below safety stock without plan order, some items it's not. Does anyone have any thoughts on what might be the cause of this?
Content (please ensure you mask any confidential information):
Below is a screenshot when it doesn't honor safety stock and Projected available balance. We're expecting a plan order on 5/24 but not seeing it.
Tagged:
0