Project Cost and COGS
Summary:
Dear All,
I have a scenario that I'm trying to get my head around:
I'm buying material to a project/task. Perform manufacturing activities and ship off the assembly to a project sales order. My understanding of the financial transactions are:
Buying Inventory to Project (Debits Inventory Valuation) collected cost to projects $100
use inventory project ($50) and labor ($50) and common stock ($20) and complete/close the Work Order (Projects get another $70 Cost) and inventory valuation debited another $70 → $170 Inventory Valuation and $170 project cost
When I ship off the Sales Order Line for that assembly, Oracle will credit the inventory for ($50+$50+$20) = $120 and debit the project clearing account.