PDSC Not able to be imported into project costing
Summary:
Hi Guru,
I was trying to do some PDSC test where I was trying to issue a project stock out using a user defined transaction types enabled with project transaction, after it's getting costed and final accounted successfully and i can see the project attributes have been successfully derived, but somehow project costing was not able to import this cost, here is the detailed step, could you please help to check if this is a expected behavior in Fusion, or i missed any setup, or there is a bug?
Content (please ensure you mask any confidential information):
Version (include the version you are using, if applicable):