Summary:

How to perform scheduled/regular database Restructure in Strategic Workforce Planning?

Content (please ensure you mask any confidential information):

Our SWP Application is already large in datavolume - we would like to perform a technical database restructure of the WFP Essbase BSO cube on a regular basis (e.g. weekly). This can be - based on my knowledge from EPM Cloud performed in different ways:

1. Manually in Calculation manager → Database Properties → Restructure

2. Manually in EPMAutomate Client Program with appropriate commands, eventually using a client computer with scheduled scripts

3. Scheduled Job: Application → Jobs → schedule → Job Type "Restructure" (not Refresh Database) and then execution now or scheduled (later)