You're almost there! Please answer a few more questions for access to the Applications content. Complete registration
Interested in joining? Complete your registration by providing Areas of Interest here. Register

How to perform scheduled database Restructure in Strategic Workforce Planning

edited Aug 16, 2024 12:19PM in Planning 1 comment

Summary:

How to perform scheduled/regular database Restructure in Strategic Workforce Planning?

Content (please ensure you mask any confidential information):

Our SWP Application is already large in datavolume - we would like to perform a technical database restructure of the WFP Essbase BSO cube on a regular basis (e.g. weekly). This can be - based on my knowledge from EPM Cloud performed in different ways:

1. Manually in Calculation manager → Database Properties → Restructure

2. Manually in EPMAutomate Client Program with appropriate commands, eventually using a client computer with scheduled scripts

3. Scheduled Job: Application → Jobs → schedule → Job Type "Restructure" (not Refresh Database) and then execution now or scheduled (later)

Howdy, Stranger!

Log In

To view full details, sign in.

Register

Don't have an account? Click here to get started!