we have requirement, where supply plan should not net off On hand if it is not meeting MOQ?
Summary:
If we have sales order of 2500 no's and on hand is 700 and MOQ is 1000, Planned order should not consume on-hand while generating the Planned Order
It should create planned order of 2500 No's. How to achieve this functionality?
Requirement is -
- Can we ignore On hand based on MOQ or any other Order Modifier?
Content (please ensure you mask any confidential information):
If we have sales order of 2500 no's and on hand is 700 and MOQ is 1000, Planned order should not consume on-hand while generating the Planned Order
It should create planned order of 2500 No's. How to achieve this functionality?
Requirement is -