Supply plan is recommending cancellation of Purchase Orders and is suggesting to create new POs
Summary:
In Supply Plan output,
- when the demand is cancelled in a week,
- there is a demand in the next week and
- there are open POs due three weeks later, system is suggesting
- cancellation of the open POs in the current bucket,
- suggesting new planned order for the next week.
However the POs are already sent to supplier and the stock is ready to ship, it is not possible to cancel the POs.
Is there a way to prevent cancellation of the POs already sent to supplier and reschedule in / out