Using Acceptable Early Days item attribute with Constrained Planning
We are implementing constrained supply plan with weekly buckets. We noticed that the item attribute Acceptable Early Days does not work as expected. For example - for an item with Acceptable Early Days set to 150, supply plan is suggesting an action of Reschedule Out for a PO with reschedule days = 93.
Does anyone know if this item attribute is not respected in an constrained plan?
Version (include the version you are using, if applicable):
24B