Due date of component planned orders
Hi,
I believe this is not possible but still wanted to get expert opinion.
Standard functionality
- If Make Planned Order start date = 28-Sep then due date of it's component items = 27-Sep ( Component due date = start date of parent Planned Order-1 )
- If Make Work Order start date = 28-Sep then due date of it's component items = 28-Sep ( Component due date = start date of parent Work Order )
Our Requirement
Is there a way to control this? For some component items, we want the Planned Order due date = start date of parent Planned Order. (Not 1 day before FG start date but same day as FG start date).
Tagged:
0