Due date of component planned orders

Hi,

I believe this is not possible but still wanted to get expert opinion.

Standard functionality

  • If Make Planned Order start date = 28-Sep then due date of it's component items = 27-Sep ( Component due date = start date of parent Planned Order-1 )
  • If Make Work Order start date = 28-Sep then due date of it's component items = 28-Sep ( Component due date = start date of parent Work Order )

Our Requirement

Is there a way to control this? For some component items, we want the Planned Order due date = start date of parent Planned Order. (Not 1 day before FG start date but same day as FG start date).