“For assembly pull, operation should not complete if on-hand stock is not available?”
“If there is no on-hand stock, we should not complete operations for assembly pull. Is it possible? Usually, for assembly pull, only the last operation consumes material, so the system allows us to complete previous operations. Our business requires not completing operations if there is no on-hand stock. Is this possible in the standard process? If not, we need help with a custom process.”