Component Picking: Avoid reservation if the Stock exists in Supply subinventorySummary: Suppose Work order has a component X with source Subinventory & Locator as A. Assume Stock already exists in A, when pick process is run, the system creates mov…
-
can you add expense items as a material on a work definitionSummary: Can you add expense items as a material on a work definition? Content (please ensure you mask any confidential information): Can you add expense items(non-inven…
-
Changes in item not sync to work definitionSummary: Changes in supply type, supply subinventory and locator at item level doesn't propagate/ sync to work definition where these items are used as operation item. C…
-
Can we use manage service mapping for other modules like Work Order to setup default value for DFF?There's a requirement that when submit work order request, transfer work center value to work order DFF automatically. Now I tried to use function 'manage service mappin…
-
Predefined Serial Number for Non Standard Work OrderHi Team For the items that are set as Predefined Serial number. Business ask is to have serial Number tab (screenshot below)for the Non Standard work order. This way the…
-
How does the supplier opertaion of serialized WO make backflush transation when OSP PO receiving?Summary: Hi, When user received OSP PO, the related WO(serial unit) did not happen backflush even the supply type is set operation-pull. So I would like to know how the …
-
Is it mandatory to have the last operation as “In-House” for Outside Processing?Hi everyone, We’re trying to understand if it’s possible to have an Supplier Operation as the last operation in a work order. In our case, we tested this by setting the …
-
Is it possible to restrict a work order to release by an error message when input item is expiredSummary: There is a business requirement to let the user know that a work order cannot be released because one of the components in the work order is already expired com…
-
Release the reservation upon completion of the work order instead of upon closure of the Work OrderWhen closing the work order, a message appears stating that the reservations will be released. Is there a setting to release reservations upon completion of the work ord…
-
How to auto-populate a DFF on the work order header with the Inventory Category of the primary item.Summary: We need to populate a DFF (in Additional Information) on RMA work order headers with the inventory category of the primary item so that we can use that field to…
-
Want to return and install items to a child asset location that is different to the WO assetSummary: If a WO is raised against a parent Asset (e.g. Engine-01), is it possible to issue and return items against a different child Asset Number (e.g. Turbo-L/H or Al…
-
Where to input processing time on a work definition?Our business does not currently use Supply Planning, Order Promising or Sales and Operations Planning. They create work orders manually when ready to make an item. The p…
-
Error with work order execution at the workstation (WIE-4426241)Summary: I have created a workstation and when trying to execute Production at this work station i am getting error as soon as i click on check in: You must be a part of…
-
Unable to change Operation sequence using Work Definition Import through FBDISummary: I am loading an FBDI file to change the Operation sequence on work definitions. The first process - Load Interface File for Import - has completed successfully.…
-
how to scan the part number in redwood when QR code has part number and lot numberHi Team, I am trying to use the work instruction solution in manufacturing and while completing the work order in Redwood UI I wanted to scan the part number but our pro…
-
Returning different material to the Work OrderHello Team, Is there a way in Oracle Cloud Manufacturing to return a different material/component that was not issued to a work order? We have a business requirement whe…
-
How to avoid Cost Variance during WIP Product ReturnSummary: Customer is producing same item in three plants. The cost of production is different in all three plants (due to changes in resource rates and overheads). Cost …
-
The supply line is in exception because the quantity was reduced in the execution documentHello, I'm trying to create make order through sales order using Back-to-Back. I'm facing Following error, The supply line is in exception because the quantity was reduc…
-
Lot Number not getting automatically populated during orderless returnLot Number not getting automatically populated during orderless return, also unable to select Lot number manually aswell. Please find the attached screenshot for your re…
-
Printing Work order attachmentsSummary: We would need to print the Work order Attachments with the component list : The Work Order Traveller is not cutomizable, and has too many useless information in…
-
Addidng Work Order Miscellaneous cost which is done by external Supplier/other SourceHello, We have a requirement to add additional costs to a work order. For example, we operate a pipe manufacturing business where direct costs are incurred through raw m…
-
"Define Tasks" under instructions is disabled in work definition screenSummary: "Define Tasks" under instructions is disabled . What setup is missing ? Content (please ensure you mask any confidential information): Version (include the vers…
-
The attachment option when operator checks in to a work station to perform the operationSummary: How to add document to the attachment option when operator checks in to a work station to perform the operations? Apart from workstation attachments, there's an…
-
After a Work Order is Closed, the Allocated, Picked Quantity update to 0.Summary: We have setup discrete manufacturing. In 25C Oracle Fusion Env. Scenario: Work Order with Finish Good having Raw Materials are created with Supply Type as Assem…
-
Validate resource instance against continuity or number of hours logged over a given period?Summary: We have a requirement to prohibit a resource instance from executing on a work order if their continuity is not up-to-date (for example: a welder continuity whe…
-
Onhand Quantity to be gone negative only for Non - Lot Controlled itemsWe have requirement to Let Inventory drive negative on the below scenarios. FG Supply Type Lot CTL Lot Onhand Required Requirement WIP Completion Product FG1 Yes Complet…
-
How to configure service mapping to auto populate priority field on Work orders released from MRPSummary: We have a scenario where we want to populate the Priority field on the work order whenever a planned order released by planning creates a work order through orc…Arijit Dutta 6 views 1 comment 1 point Most recent by Raj C -Oracle Supply Chain Planning and Collaboration
-
Work Definition Operation Items DFFs available only in Assigned ItemsSummary: We have a business requirement to copy certain DFF values setup in Item Structure->components to the Work Definition->Operation Items 2. As standard Oracle does…
-
How to add the workstation to an operation transaction by REST API serviceSummary: We need to add the worstation to an operation transactions created by REST API service Content (please ensure you mask any confidential information): Version (i…
-
Error release plan order make item in supply chain orchestrationHi, I have released a plan order for make item. When I run supply chain orchestration it got below error : The work order wasn't created because the provided Default wor…