Is there a way we can delete the Currency in the Planning Currency?
Summary:
The idea is, in the workplan. The Resources(Indian Resource) planning currency displayed rates in the task is set to INR. But the user wants to display it in GPB.
In the Project Settings, Planning Currency it was GBP and INR.
Since we want to display currency rate in GBP, I tried to delete the INR but got an error."You can't delete the selected currency. Planned or actual amounts are already entered in this currency".
So is there a way how do I change the currency displayed in the workplan?
The other Idea of mine is to edit the resource details but it takes hours since there is more resources in the task.