How many levels does cost roll up consider for phantom in oracle cloud?

Summary: How many levels does cost roll up consider for phantom in oracle cloud?

Content:

We have an FG 101277, under which 111103 is phantom. This phantom has one component 100537 which has two sub-components 10239 and 2982. For FG, we have work definition where 111103 is also a phantom. Following is a screenshot of structure.


When we roll up FG (101277), phantom (111103) also gets rolled up with details from item structure. We are rolling FG in two following ways.

  1. Roll FG with scope "Selected Items" for 101277 only. In this case, roll up is considering items just one level below the phantom. Unit cost of 100527 is $4.69409. We have not selected "Single-level Cost Rollup" for this. Below is the screenshot of roll of phantom.