How to define Queue time for manufacturing part
Hi,
In our work definition, we set the lead time to 8 hours to produce the component. However, in reality, it takes 1 week to produce the component, even though the actual production time is only 8 hours. Is there a process to plan queue time for the items so that our system suggests start times a bit earier?