Issue with Loading Data into "Budget Adjustment" in EPBCS to Fusion Budgetary Control Cube
Hello All,
We were able to successfully push data into the initial budget in the Fusion Budgetary Control cube.
Now, we are trying to push budget transfers into the "Budget Adjustment" area. However, after reviewing the Data Load Rule (DLR), we noticed there is no option to map these fields, and the budget transfers are automatically loaded into the initial budget.
Question 1: Does anyone know where we can map these fields in Data Management so that they are correctly loaded into the "Budget Adjustment" section?
Currently, our outbound process from EPBCS to the Fusion Budgetary Control cube loads data under the Initial Budget (Balance Amount). However, we are trying to implement an additional process to load data under Budget Adjustment.