Capacity / Resources Requirement calculation for Phantom subassemblies
Summary:
Hello All,
How is Capacity / Resources Requirement calculated for Phantom subassemblies in constraint supply chain planning? supply planning doesn't calculate planned orders for phantom subassemblies since its a non stock able item. But, we have a requirement to calculate the resources capacity for the phantom sub assemblies.
In EBS we see a reference in the guide (Refer below statement). Is the process same in cloud ?
The resource requirements loaded from Oracle Bills of Material are also used by rate-based CRP when calculating rate requirements on production lines. Resource requirements are based on the effective date ranges in routings. Resource requirements for phantom assemblies are included in the requirements for the planned orders of their parent assemblies.