Capture Financial Progress on a project - ETC and EAC Calculations
Summary:
EAC amounts are getting changed when the capture progress is run multiple time for a period. For testing purposes, we booked cost for a project for the period Dec-24. Captured the progress. The ETC and EAC amounts are calculated correctly.
Booked some more cost in the Period Dec-24 and ran the capture progress again. When we ran the capture progress again for Dec-24, previously generated ETC is not changing. Due which, EAC (Actual cost plus ETC) amount is changing.
Eg:
Planned and baselined amount: 10000
Cost booked: 1000
Capture progress:
ETC and EAC are 9000 and 10000 respectively
Additional cost booked for the same month: 500