Buy Planned Order with status "Firm" is calculating wrong Suggested Start Date
Notes:
- Manufacturing Plant Calendar - 6 days working, Sunday holiday
- No supplier capacity calendar
As per standard oracle behaviour, If there is no supplier capacity calendar then processing days of Buy Planned Order should consider all 7 days as working, suggested start date of the Buy Planned order should be calculated by considering all 7 days as working days.
See below screenshot to know how suggested start date is calculated for NOT FIRM Planned order.
Processing lead time of the item is 24 days
Change it's status to FIRM > Ran the plan without refresh
suggested start date changed, now it consider sunday as holiday