how to allocate entire planning amount to one period in oracle fusion PPM forecast
Summary:
Hi,
One of our customer wants to allocate entire planning amount to one particular period in forecast in fusion PPM.
Is there ay way we can restrict planning amounts to given period only instead of spreading it to multiple periods?
Content (please ensure you mask any confidential information):
One of our customer wants to allocate entire planning amount to one particular period in forecast in fusion PPM.
By using FBDI we are uploading forecast amount for particular future period (Ex:Jun-25), when we check in UI it showing for Jun-25 period only but when we refresh actuals in forecast version it's spreading the allocated amounts to multiple period based on spread curve on the forecast line. Is there ay way we can restrict planning amounts to given period only instead of spreading it to multiple periods?