Was the roll up for work center overhead changed in 24D?
Summary:
Costs appear to no longer be properly rolling up work center overhead on phantoms after the 24D patch was applied.
Content (please ensure you mask any confidential information):
Has anyone else noticed this? The standard costs in at least one of our client's cost organizations are not rolling up to include work center overhead on phantoms. It appears to be related to the resources being broken out by level. To test this, we went back to a previous instance which had not been touched since last October and re-did the roll for one of the items. Despite no changes being made to the BOM and work definition, the cost for the item rolled up $300 less than what it was previously. We reviewed all of the configurations, including