Transfer Project Costs erroring due to insufficient funds
Summary:
We are trying to transfer costs from one project to another, and there is ample budget available in the accepting project, but we are getting errors due to insufficient funds.
I have checked the project that is working vs one that is not, and cannot figure out the difference, except that the project budget in manage project budget is missing costs? I am not sure what else to look for.
Currently this is happening to two projects and the example provided here is for Project 80090.
Content (please ensure you mask any confidential information):
See attached document showing the issue.