Customize the formula for Percentage spent Revenue recognition through project process configurator
Can we customize the percentage spent revenue method formula to add a specific condition to it.
For Example: The system should not generate any revenue unless the actual cost ITD is crossing 10% of the cost budget for that Project. Also, at the same time, there should be an accounting entry generated.
The accounting entry is, initially the project cost will be in the project WIP account until the revenue is recognized, once the revenue is recognized, all the cost in the WIP account should be transferred to project cost account. Is there any way to achieve this?
Tagged:
0