Production schedule should introduce delay between different Work Orders sharing same Resource

Summary:

Our requirement is as below Assume All work orders take 3 hours to complete Work Order 1 and Work 2 are different work orders share same resource (Equipment)

and As of now, production scheduling aligns work orders as below, without any overlap.

>> Current results -WorkOrder1 -> Start time: 12 AM , End time: 3AM WorkOrder2 -> Start time: 3AM , End time: 6AM EST

We want the work orders to be scheduled in such a way that WorkOrder-2 shall start after some delay 30 mins after WorkOrder-1 ends.

>> Requirement WorkOrder1 -> Start time: 12 AM , End time: 3 AM WorkOrder2 -> Start time: 3:30 AM , End time: 6:30 AM EST