Why can't change the budget control details for a active project?
Summary:
Why can't change the budget control details for a active project?
Content (please ensure you mask any confidential information):
This is an active project. But I can't change the budget control details for it. I tried different budget version status but failed.
I changed the financial plan type that this project applied but seems it will not update to project automatically. How can I update all the active project which has been created before.
I want to change the budget control level from resource to resource and task.
Version (include the version you are using, if applicable):
Oracle Fusion Cloud Applications24D (11.13.24.10.0)