How PPV gets cost distributed in case of Multiple cost elements?
Summary:
Cost element 1 - Material: 161.33 Cost element 2- Discount: -3.22659 |
Total standard cost - 158.10341
PO Purchase details
Quantity- 50
Rate- 165.1
Distribution
Dr | Cr | |
---|---|---|
Inventory valuation | 8,066.48 | |
Purchase price variance | 188.52 | |
Purchase price variance | 161.33 | |
Receiving inspection | 161.33 | |
Receiving inspection | 8,066.48 | |
Receiving inspection | 188.52 | |
Receiving inspection | 161.33 | |
Inventory valuation | 161.33 |
How PPV gets Distributed in 188.52 and 161.33??
Content (please ensure you mask any confidential information):
Version (include the version you are using, if applicable):
Code Snippet (add any code snippets that support your topic, if applicable):
Tagged:
0