Hi,
Background
As per oracle docs, in a constrained supply plan, the planning process solves resource capacity constraints in the below order
- Moving orders to earlier time buckets (first)
- Offloading to an alternate resource. (second)
- Finally, the plan overloads resource capacity if there's no way to meet demand on time.
Above is the standard Oracle behavior
Our client prefers below order
first - Offloading to an alternate resource.
second - Moving orders to earlier time buckets
REQUIREMENT
As per our client's business requirement, "Offloading to an alternate resource" is their first priority and "offloading to earlier time buckets" is their second priority. Is this possible? They have suggested below two options to try.