Supply Plan does not plan transfer order from 1 org to other for raw materials.Why?
Summary:
Supply Plan does not plan transfer order from 1 org to other for raw materials.Why?
Content (please ensure you mask any confidential information):
We have a sourcing rule .transfer is rank 1 and 2 and buy is rank 3
Planning does not suggerst to transfer the onhand stok from org1 to org 2 and then create a planned a planned purchase order.
Version (include the version you are using, if applicable):
Oracle Fusion Cloud Applications24D (11.13.24.10.0)
Code Snippet (add any code snippets that support your topic, if applicable):