requested delivery date refreshes agreement source lines
Summary:
Hi,
We have an unexpected behavior for PO that are sourced from agreements. Create a new PO, entering agreement and agreement line. When entering the requested delivery date on the PO line, the system refreshes the agreement and agreement line information if any other agreement or agreement line are present for the same item.
If a line is for example linked to BPA1, line 1, when the user changes the requested delivery date, the system selects any other BPA and BPA lines available for example BPA1, line 2.
This is unexpected as the BPA information have been already selected from the user. This behavior is happening also using the Add from Catalog feature where it should not happen as the user has already selected from catalog the agreement and line that it is supposed to be used. No automatic refresh is needed.