Resource usage basis type fixed and variable for same resource within same operation
Summary:
Resource usage basis type fixed and variable for same resource within same operation
Content (please ensure you mask any confidential information):
We have a requirement where for product FG, there is Operation OP-1 having resource RES1 which has fixed & variable resource usage. We cannot add same resource multiple times into same operation when defining the work definitions.
Could you please advise how do we achieve this?
Ex: Product FG
Work Definition : OP-1, RES1, Basis type Fixed with usage of 1.5 hours
OP-1, RES1, Basis type Variable with usage of 1 hour