how to prevent Supply PLan to reschedule orders in/out for a small number of days

Summary:

Damper days for Fsuion supply plan. We get thounsands of reschedule in/out daily. Most are fine tunning moving orders 1 to 3 days. How to damper fusion to reduce noise?

Content (please ensure you mask any confidential information):

In JDE MRP there is a "Damper days" parameter that prevents the creation of irrelevant messages that cause noise and affects planners productivity because they need to review every single msg to decide if it is legit or not.
The damper days works by setting a limmit of days before and after the order date. Any changes withing that date range does not trigger a plan message like reschedule in or reschedule out.