Supply Orchestration Issue
Hi,We have a scenario where item which has a onhand but it is already reserved against a different order but still on the sales order Supply planning thinks there is an existing onhand and does not go for new Work order creation which is delaying the supply and the sales order shipments in turn. GOP Collection Planning is scheduled to run every 15 minutes and it takes parameters like on hand, sales orders and transfer orders .
There is another scenario where there is a manual TO and even that is being considered as a supply due to ATP rule setup accordingly.