Resource Rate show different value after decimal than what is loaded using Cost Scenario.
Summary:
For example- user have loaded the Resource Rate as 0.006525. While checking the Resource Rate (Using Manage Resource Rate page), application shows the 'Total Rate' as 0.00653, But if user clicks on the 'Total Rate' hyperlink, user can see the rate as 0.00652 and this value (i.e. 0.00652) is used to calculate the Cost Roll-up.
Thus user has difference in Resource Rate values in 2 different pages for the same Resource.
Content (please ensure you mask any confidential information):
Refer the Attachment
Version (include the version you are using, if applicable):
Oracle Fusion Cloud Applications24D (11.13.24.10.0)
Code Snippet (add any code snippets that support your topic, if applicable):
Tagged:
0