Resource Owning Burden Rate Multiplier for Cross Charge Project Planning
Hi Team,
We have a scenario during cross charge project planning expecting burden rate should be applied from resource owning organization instead of project / task owning organization.
Scenario : We have burden rate schedules for labor costs and defined at business unit level. BU_NZ is the project owning business unit and deploy resources from other entities like BU_AU, BU_ID etc.
Have burden multipliers for labor cost expenditure type.
BU_NZ : 1.3
BU_AU : 1.5
BU_ID: 1.8
If we are planning BU_AU resource on ABC project owned for BU_NZ. For all resources application considering the burden multipler as 1.3. Customer expecting resource owning business unit burden rate should be applied.