PRJ: Revise budget is getting allocated to previous months for which progress is already captured
Summary:
Dear Team,
Revised budget for the task is getting equally distributed over the task duration.
Here the expectations are, if the progress is already captured for those months then revised budget should not allocate to particular months. it should allocate remaining duration.
Kindly advise how to achieve.
Regards,
Prashant kadlag