Purchase order pre-processing days in OTBI
in Purchasing
Summary:
Content (please ensure you mask any confidential information):
We are using the Purchase Order Pre-processing days metric in my OTBI report. We are using this column as is. But we are unable to understand the way the numbers are calculated in this column. Need assistance with this.
For instance, we on 13-Apr-2025, we created two POs converting two different PRs.
PO Number | PR Number | PR Creation Date | PO Creation Date | PR to PO Creation Lead Time (Days) | ||
---|---|---|---|---|---|---|
DAR-PO-300000911 | TZ25-1255 | 07-Feb-25 | 13-Apr-25 | 65 | ||
DAR-PO-300000910 | TZ25-1572 | 13-Mar-25 | 13-Apr-25 | 31 | ||
Both the PRs include 1 line each.
DAR-PO-300000910 was canceled. But the PR is active.