Not able to make any rate change on PO after work confirmation created for different line

Summary:

Not able to make any rate change on PO after work confirmation created for different line

Content (please ensure you mask any confidential information):

Using Complex PO with progress schedules

I understand the limitation on updating the rate (price) for a line where a work confirmation exists for that line.

However the application pevents any rate change on a schedule for ALL lines on the PO, as soon as the first work confirmation is submitted.

E.g.

  • Two lines on PO with rate based schedules
    • Work confirmation created for line 1 and approved
    • Try and update price on line 2 and receive the error