Maintenance Work Order Demand Does Not Consume Spare Part Forecast

Summary:
Maintenance Work Order Demand Does Not Consume Spare Part Forecast

Content (please ensure you mask any confidential information):

We have generated spare part forecast based on maintenance work order consumption history. We passed the generated spare part forecast from demand plan to supply plan so that spares part supplies can be planned.

But the issue we got is that maintenance work orders which are collected in supply plan too explodes the spare parts demand and it creates planned order and it does not consume spare parts forecast which was generated in demand plan and this is duplicating the spare parts demands.