Incorrect manufacturing lead time
Summary:
The lead time rollup is not calculating correct variable lead time for the item
Content (please ensure you mask any confidential information):
The lead time rollup is not calculating correct variable lead time for the item. It's a simple WD with just 1 OP and 1 resource but still Oracle is going wrong.
Resource usage: 0.05 hrs
Plant Calendar Shift: 2 shifts in calendar: 06 AM -4 PM and 4PM to 2AM.
Resource assigned to 1 of the shift: 4PM to 2AM.
Lot size: 1
Oracle calculation logic for variable lead time:
Variable lead time : (usage of the variable resource divided by the total shift duration)/lot size.