In our Production, we have PIM, Inventory, Procurement, AP, and Supply Chain Planning. Currently, we have 4/4/5 facility schedules for Inventory org and cycle counting - but with different workday patterns.

Due to the business requirements, we are trying to assess the impacts of changing the Inventory Org Facility Schedule - from 4/4/5 to Gregorian Monthly schedule.

Content (please ensure you mask any confidential information):

1.    What would be the impact of changing the current Inventory Orgs 4/4/5 Facility Schedule with 7 workday patterns to Gregorian – across the above Fusion products?

a.    Can we change the Facility Schedule for the Inventory Org since it’s live in Prod and has historical transactions?