Project Cost and Commitment are not Visible in Project Financial Progress
We have configured the Fusion Project for Capital Project functionality.
So we have followed the implementation guidelines for defining Capital Projects.
After completing the Project Setups, We have created Purchase Requisition, Purchase Orders, PO Receipts
We have also enabled the Project Performance Reporting KPI measures to track the Committed Cost and Actual
However we are unable to view the information on the Project Financial Progress.
Also note update Project Performance has been executed multiple times to update the Project Performance
0