Safety Stock Planning with Lead Time Constraints

edited 10:57AM in Supply Chain Planning and Collaboration 1 comment

Summary:

Hi Guru,

i was reading the supply planning user guide for the examples of Safety Stock Planning with Lead Time Constraints and got confused:

Example of Safety Stock Planning with Lead Time Constraints

if the purchasing lead time is 3 days, and there is 40 demand on day1 because of the safety stock, why the planned order have to be pushed to day 4? shouldn't the plan order be suggested 3 days earlier(day-4) to meet this demand, and then compressed to day1 since it's the start date of the plan?


Content (please ensure you mask any confidential information):


Version (include the version you are using, if applicable):

Howdy, Stranger!

Log In

To view full details, sign in.

Register

Don't have an account? Click here to get started!