Lead time constrained plan
I have a question about lead time constrained plan
I have a item with the next work definition
Lead time calculate but this item is
I have a planer order with quantity 15104
For me lead time should be Fixed + Variable * planned quantity = 0.00943*15104 + 0.5 = 142.43072 hs or 5.93461 days
But plan shows
Suggested Order Date is ok by preprosecing lead time 2 days.
But y think the other days shouldn't be equals.
Please could you help me Understand that.
I found this information in documentation but procesing I understad is fixed * variable * quantity planned order, isn't it?
Tagged: