Inventory Activities not coded to Projects are triggering Project Costs

edited 10:34AM in Project Management

Summary:

Inventory Activities not coded to Projects are triggering Project Costs

Content (please ensure you mask any confidential information):

Hi,

This is a bit of a long one…

A customer I support uses Inventory, Cost Management and Project Costing.

Edit: I have asked the same question 3 times, one for each of the above modules, since this issue is related to all 3 modules. Links to the posts: Project Management, Costing, Inventory Management.

🟢Subinventory Transfer

End point in Projects - an Expenditure Item linked to a Misc Transaction in Inventory:

Screenshot001

  • Transaction Source: Oracle Fusion Cost Management
  • Document: Miscellaneous Inventory
  • Source Transaction Type: Project Issue