Unable to Apply the Leaves all night shift employees
Summary:
Hi Team,
We are facing an issue where users are unable to apply absence with the correct absence start date and start time.
Example:
Based on the work calendar:
Shift Start: 26th Dec
Shift End: 27th Dec
27th Dec is an off day
When a user applies absence starting on 26th Dec, the system is calculating the absence duration as 1 day on 27th Dec, instead of 1 day on 26th Dec.
Users expect the system to consider 26th Dec as the first day of the absence (Duration = 1), but the system is incorrectly pushing the duration to 27th Dec, which is an off day.