We have 2 requisitions which share same details such as Requested delivery date, ship-to location and ship-to organization, Destination type, item. We want to process both requisitions (REQ1 and REQ2) together into one Purchase Order, it shows two different behavior in two different environment -
TEST Instance - It grouped and created 1 line on the purchase order with sum of quantity, with two 2 schedule lines on the purchase order.
Dev-1 Instance - It does not group the lines on the purchase order, meaning it has two line 1 and line 2 , with two 2 schedule lines on the purchase order.
All the setup are exactly same in both the environment.