Setup end date as last day of month
Summary:
We have configured a profile with the following settings:
- Start day offset: 5
- Preparer duration: 10 working days
- Reviewer duration: 3 working days
- Working days: Monday to Friday
For the month of February, the calculation works as follows:
- Day 5 falls on 6th February
- The item shows with the Preparer with 20th February as the end date
- It shows to the Reviewer, with 25th February as the end date
However, when holidays are present, the timeline gets extended.
Example:
If 16th February to 20th February is a holiday period, the schedule changes to:
- Day 5 remains 6th February
- The item shows with the Preparer