Work orders inside an FTF is being elapsed to next day of the schedule

Summary:

We have a Work order which was released on 16-Feb-2026 in Released-Firm status. This Work order was collected to PS in the latest run and we noticed that it was elapsed to the next day which is out of the FTF. So, we added enough resource availability to the resource and then Refreshed and Solved. The Resource availability was visible in the Gantt chart, but the Work order did not get accommodated for 16th.

We increased 2 hours of the shift. The second and Third operation of the WO, takes 1 hr 5 minutes to complete which means there is enough time to schedule the WO for 16-Feb. But PS is not considering that availability and elapsing the work order to 17th. Does this have anything to do with the FTF setup ?

Howdy, Stranger!

Log In

To view full details, sign in.

Register

Don't have an account? Click here to get started!