You're almost there! Please answer a few more questions for access to the Applications content. Complete registration
Interested in joining? Complete your registration by providing Areas of Interest here. Register

WMS PROD refresh from recovery point

Hi All,
We are implementing Oracle WMS cloud with Oracle Retail cloud.


Retail/ Retail Insight have planned a cutover dress rehearsal before the final cutover takes place. By instructions of Retail Cloud operations team they have to use the Production. It will be good to have the same approach with WMS PROD.


Can we follow the approach of Retail/ Retail Insights with help of recovery?


The steps to follow at high level can be:
#After a successful UAT: configure the WMS PROD.
#Set a recovery point for WMS PROD.(Point 1)

By following the cutover plan (dress rehearsal):

#load and validate the WMS DM objects

Howdy, Stranger!

Log In

To view full details, sign in.

Register

Don't have an account? Click here to get started!