Hi all,

I am trying to use ADFDI "Manage Work Definition in Spreadsheet", specifically the Operation Resources tab but keep getting errors when attempting to upload.

Currently, we have over 800 items that have 2 resources: 1) Equipment, 2) Labor. The way they were setup originally had equipment with resource sequence = 10 and Labor with resource sequence = 20.

I want these to be the same sequence, as Labor + equipment work in parallel, not one after the other to make the items.

To do this, I went in and changed the equipment to some sequence=50 and uploaded successfully. Then, I updated all labor from sequence = 20 to sequence 10, because I want equipment to be principal and not labor. So, after all labor was set to sequence 10, I went back and tried to update equipment from 50 to 10 as well as setting the Principal Flag to Y. So that both equipment and labor are resource sequence 10, with equipment as principal.