Unconstrained SP: Lead time calculation and due date logic for supplier operations (OSP)

Summary:

Hello,

Could someone help me understand how supply planning works for Outside Processing operations.

Item A has four components: B, C, D, and E. The work definitions are as follows:
Since each resource's assigned unit is 1 and the shift is 8 hours, OP10, OP20, and OP40 each require one day.

Operation

Type

Operation Item

Operation Resource

Resource Usage (Variable)

Supplier Operation LT (Variable)

OP10

In-house

B

R1

8 Hours

OP20

In-house

C

R2

8 Hours

OP30

Supplier

D

8 Hours (1/3 day)

OP40

In-house

E

R3

8 Hours

  1. When I run "Calculate Lead Times and Roll Up Cumulative Lead Times," the variable lead time for item A is 3 days.